The committee charged to review, restructure and recommend areas of amendment of the Ameri power deal, has recommended that the deal be re-negotiated or abrogated on grounds of fraud, after it emerged that Ghana was made to pay 150 million dollars extra in commission to Africa & Middle East Resources Investment Group LLC (Ameri Energy) for the construction of the power plant.
Ameri in its agreement with Government dated February 10th, 2015, charged Ghana significantly higher than what it was charged by the Turkish registered company – PPR, which financed and executed the project.
The Turkish firm pegged the total cost of the project which is to span over a 5 year period at a maximum of 360 million dollars.
Bloated Commission?
However in the Build Operate Own Transfer (BOOT) agreement signed between Government and Ameri the deal was pegged at a minimum of 510 million dollars.
Leaving Ameri with a commission of 150 million dollars.
According to the 17 member committee inaugurated by the Energy Minister Mr. Boakye Agyarko on February 01,2017 to review the Ameri power deal, on grounds of that anomaly, as well other financial, technical and legal issues, the power company must be made to re-negotiate the deal or be rejected by Government on grounds of fraud.
The deal was signed as an emergency power agreement on the 10th of February, 2015, between Government of Ghana represented by the Minister of Power and Ameri Energy, to help reduce the country’s power deficit at the time.
According to the Committee chaired by private legal practitioner Mr Philip Addison, though the plant is currently operational a number of omissions and concessions made in the agreement are not only unfair but also not in the interest of Ghana.
Other Revelations
According to the committee’s report the Ameri Energy plant currently does not have an operating license.
The development, the committee states, is contrary to section 11 and 25 of the Energy Commission Act, 1997 (ACT 541) which requires the operators of the plant to secure the licenses and permits.
The committee urges that Ameri Energy must get the required license and permits as soon as possible.
It adds that a Grid Interconnection Agreement must also be signed between the plant operator and the Grid operator (GRIDCo).
Meanwhile the Energy Commission (EC) is reported to have officially notified VRA that the Ameri 250MW plant is yet to secure an operational license.
Ameri and its third parties paid no taxes in Ghana.
The report also revealed that Government at the time also approved a wide exemption of taxes for Ameri and its third parties.
The maove meant that Ameri and all its affiliates and sub-contractors and third parties were not liable to pay any form of tax whatsoever in Ghana.
The Committee in its report stated that the move was not acceptable and directed that moving forward, contractors must be made to pay taxes such as corporate and income tax.
No due diligence was carried out on Ameri
According to the Committee’s report no due diligence was carried out on Africa and Middle East Resources Investment Group LLC (Ameri Group) nor Ameri Energy Power Equipment Trading LLC (Ameri Equipment).
Consequently GoG has no information on the shareholders and directors on either company.
Meanwhile, despite the Deputy Attorney General being present during negotiations and execution of the Agreement, there was no legal opinion on Ameri from the AG’s Department.
The committee recommended that in the future legal opinion from the AG’s department must be sought, to ensure that Agreements conform to the laws of the country.
Engineers and Planners paid for unfinished work
The committee also revealed that Government had the sole responsibility under the Agreement to provide a cleared, levelled and compacted site acceptable to Ameri Energy for the installation of the equipment.
This activity was contracted by Government to Engineers and Planners (E&P).
According to the report the two tasks under this responsibility remain to be completed by E&P namely, spread of gravel on the lay down area to Ameri’s specifications, and perimeter and access roads to the site.
But the report states that E&P have demobilized from the site without completion of the works, which it states is a breach of E&P’s contract with GoG.
Adding that it has been informed that Government has paid E&P for all works undertaken to date.
The outstanding activities have dire implications on the operation of the plant such as frequent replacement of air filters due to excessive dust, which negatively impacts on the plant’s availability, the report said.
Join GhanaStar.com to receive daily email alerts of breaking news in Ghana. GhanaStar.com is your source for all Ghana News. Get the latest Ghana news, breaking news, sports, politics, entertainment and more about Ghana, Africa and beyond.